Shoham Data Center | Case Study

Project Overview

The Shoham Data Center is a 4-storey critical facility designed to provide secure and reliable infrastructure for digital operations. Like many modern data center projects, it required large volumes of reinforced concrete to be constructed under an aggressive schedule while maintaining strict quality requirements. The project included 500-mm-thick reinforced concrete floor slabs, with each concrete pour totaling approximately 200 m³. With a demanding construction timeline and significant concrete quantities involved, improving construction efficiency and optimizing material use were key priorities for the project team.

Looking for a Smarter Way to Optimize Concrete

The project was led by Head Site Engineer Israel Glick, who had previously implemented GreenVibe on two other construction projects. Based on his experience with the system, he recognized the potential to use real-time concrete data to reduce unnecessary cement consumption while maintaining construction progress. The structural design required 30 MPa concrete, but the contractor initially selected a more conservative C50 mix. The stronger mix was chosen to ensure the concrete would achieve the required early strength for formwork removal after seven days, since the cost of extending formwork use was significantly higher than the cost of using a stronger concrete mix.

Israel Glick believed that if the actual strength development of the concrete could be verified inside the structure, the project could safely return to the specified C40 mix, reducing cement consumption and material costs without affecting the construction schedule. Before implementation, the structural engineer tested and validated the GreenVibe system to confirm its suitability for the project. Following approval, GreenVibe was introduced to provide continuous visibility into the actual strength development of concrete strength and temperature throughout construction.

The First Pour Revealed More Than Expected

During the first concrete pour, GreenVibe identified that two different concrete mixes had been supplied within the same pour. This provided the project team with immediate visibility into the actual concrete placed in the structure, something that would not have been identified through scheduled testing alone. The monitoring also confirmed that the concrete was developing strength faster than expected. Instead of waiting the planned eight days to remove the formwork, GreenVibe data confirmed that the concrete had already reached the required compressive strength of 30 MPa, allowing the contractor to remove the formwork confidently after just 4.5 days. This early confirmation accelerated the construction cycle and demonstrated the value of understanding concrete behavior within the structure.

From Conservative Mix to Optimized Mix

With confidence in the monitoring data, the project team was able to use the specified C40 mix rather than the overly conservative C50. This reduced cement consumption while maintaining the required structural performance and construction schedule. Throughout the project, GreenVibe continued monitoring the concrete performance and provided the data needed to make decisions based on actual in-place conditions rather than assumptions.

Project Outcome

Across the project’s concrete castings, GreenVibe provided the project team with the confidence to make faster construction decisions while optimizing concrete usage. The continuous monitoring confirmed that the required 30 MPa strength for formwork removal was achieved significantly earlier than expected, allowing the contractor to release formwork after 4.5 days instead of the planned 8 days. This accelerated the construction cycle and reduced the costs associated with extended formwork retention. The real-time data also enabled the project team to transition from the conservative C50 concrete mix back to the specified C40 mix. This optimization generated approximately $2.3K in concrete mix savings per pour, reduced cement consumption, and lowered embodied carbon by approximately 10 tons of CO₂ per pour. In addition, the improved visibility into concrete strength development reduced the need for additional formwork equipment rotation, generating approximately $1.7K in savings per pour.  

Access to real-time in-place strength data eliminated the need to wait for laboratory test results, enabling construction decisions to be based on the actual in-place performance of the concrete rather than on predefined schedules. The Shoham Data Center project demonstrated how continuous concrete monitoring can create measurable value throughout construction, accelerating progress, reducing costs, and supporting more sustainable material decisions without compromising structural performance.