Highway 22 Bridge | Case Study

Optimizing the Construction Time for Every Bridge Segment

The Challenge

The Highway 22 bridge project relied on traveling formwork and post-tensioned concrete construction, where each bridge segment had to achieve the required compressive strength before post-tensioning could begin and the formwork could advance to the next pour. Under the conventional workflow, these decisions depended on laboratory compression tests performed on concrete cylinders and cubes. While reliable, the process often introduced unnecessary delays because samples had to be transported, tested, and reported before work could continue.

For a project built around repetitive construction cycles, every extra day spent waiting slowed progress and extended the overall schedule.

The Solution

Greenvibe introduced continuous, real-time concrete strength monitoring through wireless sensors embedded directly inside every bridge segment. From the moment the concrete was placed, the project team could monitor temperature, maturity, and strength development within the actual structure rather than relying solely on laboratory specimens.

After approval for production use, the system became part of the project’s standard construction workflow, providing engineers with immediate visibility into the condition of each bridge segment and allowing them to make decisions based on real-time field data.

The Results

The first production pours quickly demonstrated the value of real-time strength monitoring. During one monitored pour, ambient temperatures reached 34°C, while the concrete’s internal temperature climbed to approximately 75°C as hydration progressed. Greenvibe showed that the concrete achieved approximately 70% of its required strength within just 24 hours, giving the project team early confirmation that the structure was progressing as expected.

The project manager ultimately chose to proceed after 48 hours. Under the conventional process, similar bridge segments typically required five to six days before post-tensioning operations could begin. Real-time visibility into in-place concrete strength shortened the construction cycle by three to four days for every bridge segment while maintaining the confidence required for critical engineering decisions.

Greenvibe is expected to monitor 18 bridge segments throughout the project. The accumulated schedule savings are projected to exceed 60 days, representing an estimated value of nearly $300,000 USD based on project costs of approximately $5,000 USD per day. The project demonstrated that real-time concrete monitoring can accelerate bridge construction, reduce schedule risk, and give project teams faster access to the information they need to keep work moving safely and efficiently.